NO.124 As a result of improper machining, a gear-tooth in a vehicle’s transmission breaks causing the transmission to lock up and the vehicle to crash, injuring the driver. The failure mode in this case should be identified by the reliability engineer as the Response:

 
 
 
 

NO.125 Which of the following graphs represents a product that is a good candidate for an accelerated degradation test involving overstress testing?

Response:

 
 
 
 

NO.126 A satellite has two redundant control systems, each has a failure rate (lambda) = 1×10 -6 failures/hour. If one of the systems fails, the failure rate for the remaining system increases to 2×10 -5 failures/hour.
What is the reliability of the redundant control systems at 175,000 hours?
Response:

 
 
 
 

NO.127 The department having the authority to sign all deviations pertaining to the design of the product is normally:
Response:

 
 
 
 

NO.128 A plastics plant operates 8 extruders producing plastic film. Production volume requirements cannot be met if less than 6 extruders are operating. There is a .30 probability that a machine stopping malfunction will occur.
What is the probability that 6 extruders can remain operating throughout the day?
Response:

 
 
 
 

NO.129 All of the following statements concerning statistical inference are true EXCEPT:
Response:

 
 
 
 

NO.130 The rated breaking strength of a suspension bridge cable is 150,000 pounds. An example using this cable in a derated condition is which of the following?
Response:

 
 
 
 

NO.131 The continuous improvement process can be guided by several techniques. Which of the following is the BEST approach?
Response:

 
 
 
 

NO.132 Human factors in product safety planning are assessed for which of the following reasons?
I. To allocate the proper balance between man and machine.
II. To address the limitations of human beings.
III. To determine the user hardware interaction.
Response:

 
 
 
 

NO.133 An employee is injured on the job. The employer has proven to have a good safety and health program.
Generally the employee has which of the following options available to him/her?
Response:

 
 
 
 

NO.134 In a software development project, which of the following elements is NOT essential to ensure a reliable product?
Response:

 
 
 
 

NO.135 In the area of risk assessment, hazard severity categories are used to provide a measure of the seriousness involved. A system failure causing major environmental damage would be classified as:
Response:

 
 
 
 

NO.136 Failure data are analyzed and a proportion of items survive to the end of the test. Data on these types of samples are referred as:
Response:

 
 
 
 

NO.137 A go/no-go device is tested until it fails. If X is the number of tests to first failure with no wear out present, and the probability of success on each test is .99, then the probability that X is greater than 5 is:
Response:

 
 
 
 

NO.138 A consideration for proper part selection is:
I. Parts application and specifications.
II. Selection, control and integration.
III. Derating.
Response:

 
 
 
 

NO.139 Failure occur on a system at 75, 79, 83, 85 hours. Assuming normality, one sided and unbiased the lower tolerance limit for 95% reliability with 90% confidence for this sample is:
Response:

 
 
 
 

NO.140 In general, reliability testing is performed for which of the following reasons?
I. To detect unanticipated failure modes.
II. To compare estimated failure rates to actual failure rates.
III. To monitor reliability growth over time.
IV. To meet or exceed customer expectations.
Response:

 
 
 
 

NO.141 Who should be chairperson of a design review committee?
Response:

 
 
 
 

NO.142 Failure data collection, analysis, and corrective action:
I. Should be conducted by a competent staff using an electronic computer.
II. Is a requirement of MIL-STD-785.
III. Always pays for itself in the long run.
Response:

 
 
 
 

NO.143 Highly repetitive operations should be assigned to:
Response:

 
 
 
 

NO.144 The following reliability block diagram shows components A, B, C, D and E with reliability Ra, Rb, Rc, Rd and Re, respectively. A or B are system entry points.

On the basis of this information, what is the reliability of the system?
Response:

 
 
 
 

NO.145 In order to sustain a high system reliability in the field, it is BEST to:
Response:

 
 
 
 

NO.146 In a design team environment, the reliability function can influence product reliability principally by:
Response:

 
 
 
 

NO.147 What percentage of the material is expected to fail?
Response:

 
 
 
 

NO.148 Probability ratio sequential tests are used for products designed to operate for a long period of time.
This test is primarily based on:
Response:

 
 
 
 