NEW QUESTION 54
When scheduling the Update Project Performance Data process to run on a periodic basis, whichsummarization method would you select? (

 
 
 
 

NEW QUESTION 55
Your customer wants a team member who is assigned to a project to beable to create and submit a forecast, butnot to be able to approve the forecast. What is the default project rolethat you should assign to the person in the project to meet this requirement? (Choose the best answer.)

 
 
 
 

NEW QUESTION 56
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitmentfor $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)

 
 
 
 

NEW QUESTION 57
You have closed theproject accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)

 
 
 
 
 

NEW QUESTION 58
Your organization performs revenue recognition based on the Labor and Non-labor Burden schedule types.
Identify the setup required to enable this kind of revenue recognition. (Choose the best answer.)

 
 
 
 

NEW QUESTION 59
Identify theattribute of a project typethatdetermines if expenditure items are billable, and theamount type to be used as the basisfor transfer pricing. (Choose the best answer.)

 
 
 
 

NEW QUESTION 60
Whichfivesteps are required for the File-Based Data Import Integration option?

 
 
 
 
 
 

NEW QUESTION 61
Which two statements are true about the cross-charge method, Borrowed and Lent?

 
 
 
 

NEW QUESTION 62
You are now the project manager of a newly created implementation project. Which two items arenotpart of managing an implementation project?

 
 
 
 
 

NEW QUESTION 63
Your organization has been awarded a new contract based on which you are allowedto sell:
* Items not tracked in inventory
* Inventory items
* Services
Which contract structure would fulfill your requirement of item sales? (Choose the best answer.)

 
 
 
 

NEW QUESTION 64
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitmentfor $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)

 
 
 
 

NEW QUESTION 65
Youare implementing Project Portfolio Management for a global professional services organization. In their Consulting Services line of business, it is common to use resources from different business units based on the skills required. Therefore, cross-chargetransactions happen between business units within the same legal entity.Transfer price calculations need to be based on raw costs, with no further adjustments to transfer price.
Identify two setups that can drive this borrowed and lent agreement. (Choosetwo.)

 
 
 
 

NEW QUESTION 66
Which two statements describe how the Resource Qualification Score is calculated?

 
 
 
 

NEW QUESTION 67
Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.
Identify the correct statement about the RBS and new resources. (Choose the best answer.)

 
 
 
 

NEW QUESTION 68
While opening an organization tree on the Manage OrganizationTrees page, you notice that the hierarchy status is displayed as Inactive. Identify the two reasons for the organization tree to be in Inactive status. ( Choose two.)

 
 
 
 
 

NEW QUESTION 69
Your company creates a separate project for infrastructure services, so as to track these costs separately and then allocateto various projects that use the services of the infrastructure team. You want to allocate these costs by first attributing a fixed percentage of the source amount to each project and then spread it across tasks based on the actual labor hours charged to each task.
Which allocation basis method would you use to meet this requirement? (Choose the best answer.)

 
 
 
 

NEW QUESTION 70
Your customer wants to assign the Net 45 payment term to all sets except for the corporate business unit specific set, which is assigned the Net 15 payment term. At transaction entry, the list of values for payment terms consists of only one set of data: the set that is assigned to the transaction’s business unit.
Which reference data sharing method would you setup to meet the customer requirement? (Choose the best answer.)

 
 
 
 

NEW QUESTION 71
Your customerhas different accounting and project accounting periods, and sometimes enters invoices with an invoice date in the open project accounting and closed accounting periods. Which two statements are true about how project accounting and accounting dates willbe populated in such invoices? (Choose two.)

 
 
 
 
 

NEW QUESTION 72
You haveprojects and tasks defined with transaction controls, which does not allow certain types of charges to the project. Your business needs to create invoices in AP with this project every period and hence would like to make the process easier by creating a distribution set. As you create the distribution set, you notice that thesedistribution set lines are not validated against the project transaction controlsand you are allowed to save it without any validation errors. Identify the why the project transaction controls are not applied. ( Choose the best answer.)

 
 
 
 

NEW QUESTION 73
You havedefined two expenditure types, but they are not available for selection when youenter an expenditure batch. Identify the reason for this problem. (Choose the best answer.)

 
 
 
 

NEW QUESTION 74
Your client is involved in automation control systems installation. Over the years, they have analyzed their total project spend on specific resource classes. They have identified that their cost spread distribution factor on a 10 spread point scale resembles:
0-4-10-11-14-13-10-4-0-0. Identify two ways to handle this kind of a spread on their budgets and forecasts. ( Choose two)

 
 
 
 